Wake Spine Holiday Push
Between Christmas and New Year’s, it usually dies down a little and folks can take some time off. This year, however, no such luxury. Schedules are tighter than ever, and with more work on the way, there is no rest …
Between Christmas and New Year’s, it usually dies down a little and folks can take some time off. This year, however, no such luxury. Schedules are tighter than ever, and with more work on the way, there is no rest …
The holidays didn’t slow down progress. Inspections may have been a bit harder to obtain (to get an inspector to show up) since the City took 3 days off this week. Ho Ho! LVT Flooring is installed, ceiling tile is …
Week #8 at the North Carolina Turnpike Authority’s toll operations building renovation project showed significant progress. Ceiling grid installation and electrical work overhead is underway. Prime paint is complete. Lights will be installed next week along with HVAC diffusers and …
Construction on the Wake Spine project is rapidly nearing completion. Due to wrap up in mid-January, the renovation project is ahead of schedule. The new medical office fitup, as designed by Gontram Architecture, will be the latest location for the …
The light at the end of the extremely short and accelerated tunnel can be seen for the new Bone & Joint Surgery Clinic in Raleigh, NC. The new orthopedic clinic, as designed by Gontram Architecture, will begin seeing patients as …
Work at the North Carolina Turnpike Authority’s toll operations continues to progress. Sheetrock finishing is underway. HVAC rough-in is complete, and electrical work overhead is almost finished. Prime paint and ceiling grid work is expected before Christmas. This project is …
Work on the new Bone & Joint Surgery Clinic continues! Tremendous progress has been made in the last 2 weeks on the orthopedic clinic, as designed by Gontram Architecture. Sheetrock finishing has wrapped up, walls have been prime painted, ceiling grid …
Construction on the Wake Spine project continues at a furious clip. Progress continues at the new medical office fitup, as designed by Gontram Architecture. Prime paint is complete. Ceiling grid has been installed. HVAC distribution is complete to the grid. And, …
The 7th week of construction on the Wake Spine project picked up after the Thanksgiving holiday. Tremendous progress continues at the new medical office fitup, as designed by Gontram Architecture. Sheetrock finishing, HVAC rough-in, and electrical work overhead continued this …
The 7th week of construction picked up after the Thanksgiving holiday. Tremendous progress continues at the new Bone & Joint Surgery Clinic, as designed by Gontram Architecture. Sheetrock finishing, HVAC rough-in, and electrical work overhead continued this week. The X-ray …