The NC Retail Merchants Association project in downtown Raleigh, NC is a few mere weeks from completion.
There is still a lot to do, but steady progress is being made. Above ceiling inspections are being obtained today and early next week. Ceiling tile installation can proceed as soon as possible.
Wood trim installation, painting, etc. are at a fever pitch.
New break room, kitchenette, and copy room cabinetry are due to arrive and be installed next week. Floor finishes are also scheduled next week.
The owner’s telecom contractors have run cable above ceiling and are ready to terminate connections.
Construction is slated to be complete by June 30th. Because of the accelerated schedule, the design-build process made the most sense to NCRMA. Gontram Architecture and Ten Penny Construction have once again teamed up for this unique Design-Build opportunity. As a single-source delivery method, we control budget and schedule, taking a lot of the usual Owner-associated worry out of the project.