Coming down to the last few weeks of the Michael Jordan Collision Center project in Durham, NC.

Work recently completed includes prime paint, ceiling grid, lighting, ductwork, above ceiling inspections, and more.  On the exterior, the rear drive was poured, and the fire line and domestic water line work was cleaned up.

Rear driveway area complete

Rear driveway area complete

Body shop paint underway

Body shop paint underway

Customer Lobby

Customer Lobby

Ceramic tile underway in restrooms

Ceramic tile underway in restrooms

View from small mezzanine landing

View from small mezzanine landing

Finishing touches underway include ceramic floor and wall tile, painting in Body Shop area, ceiling tile installation, and others.

Next week, we will see VCT flooring installed, cabinetry, and plumbing fixtures. The last bit of fire sprinkler work should be completed next week as well.

On the exterior, the front driveway entrance will be repaired, fencing work completed, and landscaping may be installed.

This project is being provided to the Owner through the Architect-led Design-Build project delivery method with Ten Penny Construction, Inc.