Bone & Joint makes progress in Week 3

by

Electrical rough-in underway

Electrical and Data Rough-in

Future Reception Area

Metal stud framing is complete and electrical rough-ins are nearing completion.  Plumbing rough-ins are underway and mechanical work is getting started.  Sheetrock should begin being installed early next week.

The future 9,000-square feet tenant space will soon be home to the Bone & Joint Surgery Clinic.  The fitup construction will feature sound attenuating exam room walls, luxury vinyl tile, and energy-efficient LED lighting.

The project is being delivered through the Architect-led Design-Build process with Ten Penny Construction.