Week #9 at the North Carolina Turnpike Authority’s toll operations building showed modest progress between Christmas and New Year’s. Ceiling grid installation finished up. Mechanical work above ceiling closed in on 90% complete. Light fixtures began installation.

This project is due to be complete by late January, 2018. So far, so good.

This project is being provided to the Owner via the Architect-led Design-Build process with Ten Penny Construction.