Sprinkler Work Underway at Michael Jordan Collision

by
CREE LED high bay fixtures installed

CREE LED high bay fixtures installed

Work on the inside of the building progressed now that the fire protection permit was released.  Work on the outside, however, was stymied by wet weather, again.

Installation of the high sprinkler pipe is well underway and away from the office area.  Sheetrock installation was complete by the end of the week, with sheetrock finishing activities due to start on Monday.

Permanent power was also installed late in the week, so we were able to turn on the new CREE LED high bay light fixtures in the Body Shop area.  Emergency light fixtures were also installed.

On the outside, even with the wet weather, we were finally able to make the fire line tap into the public water main.  This was delayed because it required shutoff of several valves given the existing condition of the main.

Emergency light fixtures installed

Emergency light fixtures installed

Stair to future upper level access

Stair to future upper level access

Sheetrock installation continues

Sheetrock installation continues

Fire line tap installed

Fire line tap installed

Next week, work will hopefully continue on the rear driveway once the rain clears.

This project is being provided to the Owner thru the Architect-led Design-Build process with Ten Penny Construction, Inc.

About

Leave a Reply

Your email address will not be published. Required fields are marked *