AECOM/URS/NCTA – Week 5 Progress

by

No crazy, shoddy, prior-construction nightmares to report this week, at least not noteworthy enough to include here.

We are plugging away at the new call center facility for the North Carolina Turnpike Authority’s toll operations. Sheetrock hanging, HVAC rough-in, and electrical work overhead continued this week.  Concrete was also patched back.

This project is due to be complete by late January, 2018. So far, so good.

This project is being provided to the Owner via the Architect-led Design-Build process with Ten Penny Construction.

 